INSTALLATION STEPS OF THE PICKET RAILING (CONCRETE FLOOR)
- Take posts
- Take spindles
- Measure 2 ¾” from the top post and place top spindle.
- Screw the spindles to the post
- Screw the panel to the spindles
- Mark the holes on concrete slab
- Drill the holes on concrete slab
- Hammer the Anchor Bolts/Plugs in the holes
- Place panel/post assembly on the ground
- Place the bolts on top and tighten
- Place plastic covers on aluminum base
- Place Caps on the posts
- Place snaps on the top handrail and bottom channel.
- Always follow Ontario Building Code Requirements (height of handrail and bottom gap