Installation steps of the Picket Railing Concrete Floor

Installation steps of the Glass Railing Concrete Floor

INSTALLATION STEPS OF THE PICKET RAILING (CONCRETE FLOOR)

1) Post Assembling
Screw spindles with the posts.
2) Post installation to the ground
Drill the concrete slab to prepare for post installation.
Insert the anchor bolts in the Concrete slab
Place the post on the anchor bolts.
Bolt the post with anchor bolts on the concrete

3) Post and section assembling
Screw the entire preassembled section to the spindles in order to connect with
the post.
4) Final Touches
Cover the top of the post with the cap
Cover the Aluminum Base of the post with Plastic Covers
Cover the top handrail and bottom channels with the snaps.

INSTALLATION STEPS OF THE GLASS RAILING (CONCRETE FLOOR)

1) Post Assembling
Screw spindles with the posts.
2) Post installation to the ground
Drill the concrete slab to prepare for post installation.
Insert the anchor bolts in the Concrete slab
Place the post on the anchor bolts.
Bolt the post with anchor bolts on the concrete

3) Post and section assembling
Screw the entire assembled picket/glass section to the spindles in order to
connect with the post.
4) Final Touches
Cover the top of the post with the cap
Cover the Aluminum Base of the post with Plastic Covers
Cover the top handrail and top/bottom channels with the snaps.

Installation steps of the Picket Railing Wood Floor

Installation steps of the Glass Railing Wood Floor

INSTALLATION STEPS OF THE PICKET RAILING (WOOD FLOOR)

1) Post Assembling
Screw spindles with the posts.
2) Post installation to the ground
Drill the wood floor to prepare for post installation.
Place the post with the aluminum base over the holes
Screw the posts on wood floor

3) Post and section assembling
Screw the entire preassembled section to the spindles in order to connect with
the post.
4) Final Touches
Cover the top of the post with the cap
Cover the Aluminum Base of the post with Plastic Covers
Cover the top handrail and bottom channels with the snaps.

INSTALLATION STEPS OF THE GLASS RAILING (WOOD FLOOR)

1) Post Assembling
Screw spindles with the posts.
2) Post installation to the ground
Drill the wood floor to prepare for post installation.
Place the post with the aluminum base over the holes
Screw the posts on wood floor

3) Post and section assembling
Screw the entire assembled picket/glass section to the spindles in order to
connect with the post.
4) Final Touches
Cover the top of the post with the cap
Cover the Aluminum Base of the post with Plastic Covers
Cover the top handrail and top/bottom channels with the snaps.